(Picture credit Monolith)
LINCOLN — Governor Jim Pillen’s Data Center Task Force passed a unanimous resolution Thursday afternoon providing guidance to the Nebraska Legislature on how to protect resources, taxpayers, and local control as companies seek sites for data center development across the state.
The resolution recommends the state maintain Nebraska’s existing protections and standards for water management and public power usage, and support localities’ zoning and review authority.
The panel also called for the Legislature to provide clear, definitive policy for the structure and execution of community benefit agreements, which allow municipalities to reap additional public benefits from data centers.
“This is probably the best interaction I’ve had with state government in my entire life. I’m not saying that in a bad way, I’m saying that in a good way,” said Ron Kaminski of the Building, Construction, and Trades Council of Nebraska and Southwest Iowa.
Kearney, Papillion Give Feedback
The meeting, held at the Nebraska Department of Water, Energy, and Environment, was the task force’s third since its creation in July. It included representatives from counties, trades, public power, natural resources districts, and energy companies. It included presentations from the cities of Kearney and Papillion on how they’ve assessed, negotiated with, and ultimately welcomed data center development on the four key points the committee reviewed: water, power, land, and community benefits.
Brenda Jensen, Kearney City Administrator, walked the task force through the city’s workings in approving the Project Horizon data center, including addressing citizens’ concerns of increased electricity rates, utility bills, and noise.
She addressed the utilities question at length, observing that the annual three million gallons of water the center will use once operational is still a million gallons less than is used per hole on the average Nebraska golf course – or hardly a tenth of the city’s splash pad.
“Of that three million gallons, two million gallons is for irrigation to meet the city’s landscaping standards. It’s only one million gallons for the actual operation of the data center.”
She also mentioned the community benefit agreement, which includes more than $1 million in local investments, $20 million in property tax revenue for the county and school district, and $14 million in electrical leases once complete.
“To put that into perspective, Kearney brought in last year $16 million in our 1.5% local option sales tax. So pretty significant form of revenue,” she said.
An additional 59 permanent jobs post-construction will be lucrative, with estimated payroll of $13 million.
Mark Stursma, Deputy City Administrator for Papillion, discussed the city’s history with data centers and zoning – of the state’s 41 operational data centers, 6 are in Papillion, with another under construction.
“Our first one was in 2010, small by today’s standards. It was actually Cabela’s came to us with their first data center, it’s not Lightedge.”
He noted that the companies behind Papillion’s data centers had been good partners with regard to noise concerns from Papillion residents.
“The companies told us they never want to be out of compliance. Very risk averse… when we give tours – and there’s a lot of interest in the noise – what I have been told by people who had the concern is that they hear the traffic over the top of the data centers.”
Economic Effects
Heath Mello, President of the Greater Omaha Chamber of Commerce and member of the task force, also gave a presentation on the economic effects of data centers. With 13 presently being planned or constructed, he estimated that data centers sustained 27,000 construction jobs and $170 million in state and local taxes.
“It’s $6.1 billion in the total economic impact of the data center industry in the state of Nebraska. For a point of reference, some of you know my prior role at the University of Nebraska System, the University’s annual economic impact is $6.4 billion a year.”
Add on nearly 9,000 permanent jobs with a labor income of $1 billion, and Nebraska’s GDP increases $2.8 billion by the Chamber’s estimate, which he also argued would not come with hiked electricity bills, a point he called misinformation.
“This data shows the complete opposite,” he said. “Data centers are paying upfront as large load users for their infrastructure.”
Large load rules across Nebraska require customers of 30 Megawatts or more to fully fund their own line extensions and substation upfront, expanding grid capacity.
“They are stable customers, and they are simply reducing the rates for residential and other customers because of the stable use of energy and what they’re paying for their current electricity rates,” he said.
Three citizens spoke during public comment, including two women who were opposed to the overwhelmingly friendly tone the task force had taken toward data center development. Tom Emerson of IBEW 265 in Lincoln spoke in favor of the meeting’s results.
As they prepared to pass the resolution, Pillen committed to the room that he would not allow the task force’s guidance to be ignored should the Legislature choose one way or another to challenge local authority on the question of data centers.
“All I know is that if the Legislature was to put forward something to take away local control, I’m not signing it,” he said. “And I’m pretty confident we’ll have a veto team to stand with us.”
With the task force reaching a resolution, it is unlikely to convene again for the foreseeable future, though Pillen affirmed it would remain open. In its aftermath, the Department of Water, Energy, and Environment has unveiled an online resources hub to provide guidance on regulations and permitting.
— Lewis Thune is a College Fix writing fellow with The Plains Sentinel.
Editor’s Note: An earlier version of this article quoted Heath Mello as stating $64 million instead of $6.4 billion.